TCF Bank Stadium™ Construction
PHASE 2: 11/06 - 7/07
Street and road realignments south and west of the stadium site. Construction/expansion of surface parking north and east of the stadium.
Street work to begin as early as February, 2007. Street work includes Huron Boulevard, University Avenue, and Oak Street. Work to be done "under traffic" with temporary lane closures, but roads to be in operation throughout.
Back to Construction |
» PHASE 1: 6/15/06 - 7/15/07
» PHASE
2: 11/06 - 7/07
» PHASE
3: 7/07 - 7/09

|
|
 |